We turn complex
problems to easy solutions
February 2024
Safe unloading
February 2024
Slussen Stockholm
October 2023
Salvage of Munksunds 5an
December 2022
Merry Christmas
October 2022
Demolition Lidingö bridge
September 2022
Quay for PEAB
August 2022
Open Bookings 2022/2023
May 2022
Platform, towercrane
May 2022
Master. EMS and GE
2022
December 2022
Merry Christmas
October 2022
Demolition Lidingö bridge
September 2022
Quay for PEAB
August 2022
Open Bookings 2022/2023
July 2022
Salmon eye
May 2022
Platform, towercrane
May 2022
Master. EMS and GE
May 2022
Loading winches
April 2022
Survey
March 2022
Tugboat Arne
February 2022
OHLA subway tunnel
January 2022
Nestor overhaul
January 2022
Armands Berze
2021
December 2021
PEAB and Aarsleff
November 2021
Preparation for OHLA
October 2021
Re-class Hermes to Master
August 2021
Skanska Lock Gate
July 2021
Transport from Norway
July 2021
North Carrier first trip
July 2021
Float off lock channel
June 2021
EMS and GE Energy
February 2021
Norrströmsbron
2020
December 2020
Open bookings 2020/2021
November 2020
Extended COOP with SCA
November 2020
25 concrete platforms
October 2020
Transformator 370 ton
October 2020
Extended Quay deck
October 2020
Jack Up in Kiruna
October 2020
Delivery Lifting devices
September 2020
North Carrier renovated
September 2020
Nord Stream II
August 2020
Beams transportation
August 2020
Transportable Jack up
July 2020
Lidingö Bridge pile work
July 2020
railway bridge demolition
July 2020
Slussen Stockholm
May 2020
Lidingö bridge foundation
May 2020
Fassi 60TM on Carrier 013
May 2020
Supporter 4
March 2020
Getingmidjan demolition
2019
October 2019
Temporary bridge Lidingö
October 2019
Carrier 16 in Ålesund
September 2019
test in Swinoujscie
September 2019
Extended fairway
August 2019
Working pontoon Carrier 4
August 2019
Carrier 8 Semisubmersible
July 2019
Herakles sold
June 2019
To Fredrikshamn float off
June 2019
Upgrade North Carrier
April 2019
Mounting roof
April 2019
Concrete elements
March 2019
Aarsleff production
March 2019
New RoLo Vessel
February 2019
Icebreaking tour February
January 2019
Launching floating concre
2018
December 2018
7500 tons on Carrier 16
December 2018
Icebreaking tour December
November 2018
Carrier 16 in action
September 2018
Nuuk Bridge Installation
August 2018
Nuuk Bridge Departure
July 2018
Nuuk Bridge Construction
June 2018
Shipment of Shipsections
May 2018
Accommodation barge
January 2018
Polar Explorer on duty
2017
December 2017
Bridgeproject Finland
November 2017
Polar Explorer Upgrade
August 2017
Transport Shipsloader
June 2017
Conversion of Carrier 7
May 2017
Lodbrok Lifting vessel
April 2017
Transport 13 000 tons
February 2017
Bridge and floating quay
January 2017
Transport Bridgesections
2016
December 2016
Expanded fleet
December 2016
Extended co-operation
November 2016
Offshore construction
November 2016
Dismantling bridge
September 2016
15 000 tons foundations
August 2016
Transport accommodations
June 2016
Transportation Timber
May 2016
Viktor
April 2016
Herakles Continues duties
March 2016
Carrier 16 Upgrade
February 2016
Carrier 7 floating quay
January 2016
New Company Name
2015
December 2015
Drydock
November 2015
Steeringhouse
October 2015
Quay for 1000 apartments
October 2015
Project completed
September 2015
Conversion two barges
August 2015
Gas baloons on fire
August 2015
Upgraded performance
July 2015
Insallation 3 ramps
July 2015
De-mobilisation
June 2015
Bridge sections
June 2015
Passenger gangways
May 2015
840 Concrete Elements
April 2015
Timbertransports
March 2015
Transportable wood-plant
February 2015
Emergency Vessel
January 2015
Removing dyktalbs
2014
December 2014
New counterweight crane
November 2014
Continue breaking ice
October 2014
New pontoon
September 2014
Elements to Värtahamnen
August 2014
Workingboat Aramis
July 2014
Removing MET-mast
June 2014
Final Design
May 2014
960 pieces
April 2014
New quay
March 2014
New contract ETV
March 2014
5 years contract
2013